Johan Sverdrup Phase 2 offshore installation completed by operator Equinor

Johan Sverdrup phase 2 installation

Johan Sverdrup Phase 2 offshore installation completed by operator Equinor

9 March 2022

Following the installation of the jacket and the new module on the existing riser platform for the Johan Sverdrup Phase 2 development in 2021, the second processing platform (P2) has now been installed using the Pioneering Spirit vessel, in a single lift operation.

With the installation of the P2 platform, the remaining work for the Johan Sverdrup Phase 2 development consists of installation of the final bridge, hook-up and commissioning of the P2 platform, completion of the subsea facilities and flowlines installation and drilling of the development wells, which are progressing to schedule.

Ongoing studies indicate that the production for full field capacity can be increased to 755 Mbopd once Phase 2 comes on stream, which remains on schedule for the fourth quarter 2022.

Read more about Johan Sverdrup here.